1
00:00:02,900 --> 00:00:06,879
Mixer hire for one house
costs 600,000 riels.

2
00:00:06,879 --> 00:00:07,756
Is it direct?

3
00:00:10,206 --> 00:00:13,834
Yes, because the whole 600,000 riels
can be traced in full to that one house,

4
00:00:13,834 --> 00:00:15,434
which makes it a direct expense.

5
00:00:16,109 --> 00:00:19,572
A direct cost can be traced
in full to a cost unit;

6
00:00:19,572 --> 00:00:23,102
any other cost is indirect,
also called an overhead.

7
00:00:23,102 --> 00:00:24,967
There are direct materials,

8
00:00:24,967 --> 00:00:29,029
for example the bricks and cement
in a house, direct labour,

9
00:00:29,029 --> 00:00:32,359
for example the bricklayers,
and direct expenses,

10
00:00:32,359 --> 00:00:35,689
for example equipment
hired for that house alone.

11
00:00:35,689 --> 00:00:40,683
So name the cost unit first, then ask
whether the whole cost belongs to it.

12
00:00:41,683 --> 00:00:43,900
Take the textbook's
house as the cost unit.

13
00:00:43,900 --> 00:00:48,534
A cement mixer is hired for a flat 600,000
riels a month, only for this house.

14
00:00:48,534 --> 00:00:50,801
Can the whole charge
be traced to the house?

15
00:00:50,801 --> 00:00:54,326
Yes, so it is a direct expense,
beside the bricks and the bricklayers.

16
00:00:55,176 --> 00:00:57,336
Now the builder's yard rent of 2 million

17
00:00:57,336 --> 00:00:59,646
riels a month serves
every house being built.

18
00:00:59,646 --> 00:01:03,865
It cannot be traced in full to this house,
so it is indirect, a production overhead.

19
00:01:04,865 --> 00:01:08,565
Watch out for calling the hire indirect
just because it is a fixed charge.

20
00:01:09,137 --> 00:01:14,968
Your turn. The mixer now serves three
houses and individual use is not tracked.

21
00:01:14,968 --> 00:01:17,373
Is the hire direct to one house?

22
00:01:17,373 --> 00:01:20,143
Decide, then check your practice card.

23
00:01:24,093 --> 00:01:28,912
Remember to name the cost unit, then
test whether the whole cost traces to it.