WEBVTT

1
00:00:02.900 --> 00:00:05.543
Time sheets log 20 hours on two ships.

2
00:00:05.543 --> 00:00:07.202
What does the manager need?

3
00:00:09.652 --> 00:00:13.511
Information: a report that groups
the hours by ship and costs them.

4
00:00:14.511 --> 00:00:15.774
Data are raw facts.

5
00:00:15.774 --> 00:00:18.616
Information is data
that has been processed,

6
00:00:18.616 --> 00:00:21.079
structured and analysed for a purpose.

7
00:00:21.079 --> 00:00:24.932
The facts come from source records,
for example time sheets,

8
00:00:24.932 --> 00:00:29.733
which show hours worked, and supplier
invoices, which show what was bought.

9
00:00:29.733 --> 00:00:33.712
Grouped by ship and costed,
the same facts help managers plan,

10
00:00:33.712 --> 00:00:36.049
control the work and make decisions.

11
00:00:36.049 --> 00:00:40.154
Keep the link to the source records
so the report can be checked.

12
00:00:41.154 --> 00:00:46.042
Let's process our time-sheet figures
for a week at the textbook's shipyard.

13
00:00:46.042 --> 00:00:50.222
Workers logged 12 hours on ship
A and eight hours on ship B.

14
00:00:50.222 --> 00:00:52.859
Labour costs 10,000 riels an hour.

15
00:00:52.859 --> 00:00:55.431
Group the hours by ship, then cost them.

16
00:00:56.281 --> 00:01:02.072
Ship A: 12 times 10,000 is 120,000 riels.

17
00:01:02.922 --> 00:01:06.812
Ship B: eight times
10,000 is 80,000 riels.

18
00:01:07.662 --> 00:01:10.453
Check: 20 hours and 200,000 riels in all.

19
00:01:11.453 --> 00:01:15.148
Watch out for passing on raw time
sheets as if they were information.

20
00:01:16.148 --> 00:01:19.874
Your turn. Change only
ship B's hours to 15.

21
00:01:19.874 --> 00:01:23.600
What labour cost does
the report show for ship B?

22
00:01:23.600 --> 00:01:26.432
Decide, then check your practice card.

23
00:01:30.382 --> 00:01:36.134
Remember to turn source facts into an
answer that management can trace and use.