1
00:00:02,900 --> 00:00:05,543
Time sheets log 20 hours on two ships.

2
00:00:05,543 --> 00:00:07,202
What does the manager need?

3
00:00:09,652 --> 00:00:13,511
Information: a report that groups
the hours by ship and costs them.

4
00:00:14,511 --> 00:00:15,774
Data are raw facts.

5
00:00:15,774 --> 00:00:18,616
Information is data
that has been processed,

6
00:00:18,616 --> 00:00:21,079
structured and analysed for a purpose.

7
00:00:21,079 --> 00:00:24,932
The facts come from source records,
for example time sheets,

8
00:00:24,932 --> 00:00:29,733
which show hours worked, and supplier
invoices, which show what was bought.

9
00:00:29,733 --> 00:00:33,712
Grouped by ship and costed,
the same facts help managers plan,

10
00:00:33,712 --> 00:00:36,049
control the work and make decisions.

11
00:00:36,049 --> 00:00:40,154
Keep the link to the source records
so the report can be checked.

12
00:00:41,154 --> 00:00:46,042
Let's process our time-sheet figures
for a week at the textbook's shipyard.

13
00:00:46,042 --> 00:00:50,222
Workers logged 12 hours on ship
A and eight hours on ship B.

14
00:00:50,222 --> 00:00:52,859
Labour costs 10,000 riels an hour.

15
00:00:52,859 --> 00:00:55,431
Group the hours by ship, then cost them.

16
00:00:56,281 --> 00:01:02,072
Ship A: 12 times 10,000 is 120,000 riels.

17
00:01:02,922 --> 00:01:06,812
Ship B: eight times
10,000 is 80,000 riels.

18
00:01:07,662 --> 00:01:10,453
Check: 20 hours and 200,000 riels in all.

19
00:01:11,453 --> 00:01:15,148
Watch out for passing on raw time
sheets as if they were information.

20
00:01:16,148 --> 00:01:19,874
Your turn. Change only
ship B's hours to 15.

21
00:01:19,874 --> 00:01:23,600
What labour cost does
the report show for ship B?

22
00:01:23,600 --> 00:01:26,432
Decide, then check your practice card.

23
00:01:30,382 --> 00:01:36,134
Remember to turn source facts into an
answer that management can trace and use.